2015
Task Resource Start Finish
Project Manager Established AA 09/01/15 09/01/15
HLC Assurance Statement & Evidence File Established AA 09/21/15 09/21/15
 New Accreditation Website Established AA 10/01/15 10/15/15
 New Accreditation Sharepoint Site Established AA 10/01/15 10/01/15
Gathering of Reports and Evidence Documents Begun AA 10/01/15 10/01/15
Criterion Comittees Established, Members Recruited AA 11/01/15 11/15/15
Steering Committee Established AA 11/01/15 11/15/15
New Accreditation Website Published AA 12/15/15 12/15/15
Self-Study Goals Determined Criterion Committees 01/15/16 04/01/16
2016
Task Resource Start Finish
Criterion Committees Establish Bi-Weekly Meeting Schedule Criterion Committees 01/02/16 01/06/16
First Criterion Committees Held Criterion Committees 01/10/16 01/10/16
Survey’s Reviewed and Planned AA 01/20/16 04/01/16
Meet, Gather Information, Conduct Interviews, Consult with Working Groups, & Other Resources, Analyze Data Criterion Committees 01/02/16 11/03/16
Survey’s distributed AA 04/11/16 05/11/16
Criterion Committees Submit Draft Reports Criterion Committees 05/01/16 07/15/16
Criterion Committees review Input and Feedback and prepare final reports Criterion Committees 08/01/16 12/01/16
Criterion Committees submit final report.  Chancellor Review Criterion Committees 12/15/16 12/15/16
Slate of Site Visitors Set (thru HLC & UAMS Negotiations) HLC/UAMS 08/01/16 12/15/16
Head of Site Visit Team Sets Date to Submit Self-Study HLC 12/15/16 12/15/16
2017
Task Resource Start Finish
Steering Committee Incorporates Feedback;  Completes Final Review of Self-Study Steering Committee 12/15/16 01/12/17
Chancellor Incorporates Feedback, Posted for Campus Wide Review Accreditation Staff 12/15/16 01/15/17
Collect & Prepare Materials for Site Vistors’ Resource Room Accreditation Staff 01/03/16 03/31/17
Final Editing and Production of Self-Study & Related Materials Accreditation Staff 01/15/17 01/20/17
Self-Study Submitted (estimated date) Steering Committee 02/15/17 02/15/17
Site Visit Planning Between UAMS and HLC HLC & UAMS 02/23/17 03/30/17
Site Visit ALL 04/17/17 04/19/17